Regent Street flyover project reaches major milestone

In December, the project reached a major milestone. During the night time works, four steel bridge beams, weighing a total of 220 tonnes were installed using a 750 tonne crane.

The largest bridge beam section was 45 metres in length and was brought to site using a specialist heavy haulage vehicle. Now that the beams have been lifted into place, the bridge spans a total of 70 metres.

We are currently working on finishing the south side of the bridge, ready to be re-opened in spring 2021. Work will then start on demolishing and reconstructing the north structure, with the completion of the whole project scheduled for Spring 2022.

Pictures showing the southern bridge beam installation can be seen below:

Posted on 13th January 2021

by Charley Richardson